Click here to access the 2024 Amended Feasibility Study Update
KEY RESULTS AND ASSUMPTIONS;
Key results and assumptions for the updated Feasibility Study are summarized below.
|
Units |
2024 FS |
2021 FS |
Production Data |
|||
Mine Life (operating) |
years |
12.5 |
12.8 |
Average Process Plant Throughput |
tpd |
27,700 |
25,200 |
Average Process Plant Throughput |
Mt/year |
10.1 |
9.2 |
Average Mining Rate |
tpd |
115,000 |
110,000 |
Average Mining Rate |
Mt/year |
42 |
40 |
Total Ore Mined |
Mt |
127 |
118 |
Strip Ratio |
waste:ore |
2.63 |
2.80 |
Palladium (payable) |
k oz |
2,122 |
1,905 |
Copper (payable) |
M lbs |
517 |
467 |
Platinum (payable) |
k oz |
485 |
537 |
Gold (payable) |
k oz |
158 |
151 |
Silver (payable) |
k oz |
3,156 |
2,823 |
LOM Palladium Equivalent Payable |
PdEq. koz |
3,613 |
3,195 |
Average Annual Palladium – Payable Metal |
k oz |
166 |
149 |
Average Annual Copper – Payable Metal |
M lbs |
41 |
36 |
Average Annual Platinum – Payable Metal |
k oz |
38 |
41 |
Average Annual Gold – Payable Metal |
k oz |
12 |
12 |
Average Annual Silver – Payable Metal |
k oz |
248 |
220 |
Operating Costs (Average LOM) |
|||
Mining (a) |
$/t mined |
3.25 |
2.53 |
Mining |
$/t milled |
11.45 |
9.23 |
Processing |
$/t milled |
8.70 |
9.08 |
G&Ab |
$/t milled |
2.67 |
2.48 |
Transport & Refining Charges |
$/t milled |
4.13 |
2.80 |
Royalty |
$/t milled |
0.09 |
0.04 |
Total Operating Cost |
$/t milled |
27.04 |
23.63 |
LOM Average Operating Costs |
US$/oz PdEq |
709 |
687 |
LOM Average AISCc |
US$/oz PdEq |
813 |
809 |
Capital Costs |
|||
Initial Capital |
$M |
1,112 |
888 |
Less: |
|
|
|
Pre-commercial production revenue |
$M |
($156) |
($171) |
Leased equipment, net of lease payments during construction |
$M |
($58) |
($53) |
Initial Capital (Adjusted) |
$M |
898 |
665 |
LOM Sustaining Capital |
$M |
424 |
423 |
Closure Costs |
$M |
72 |
66 |
Financial Evaluation |
|||
Pre-Tax Cash Flow (undiscounted) |
$M |
3,387 |
3,004 |
Pre-Tax NPV6% |
$M |
1,798 |
1,636 |
Pre-Tax IRR |
% |
31.9 |
38.6 |
Payback |
years |
2.0 |
1.9 |
Net Cash Flow (undiscounted) |
$M |
2,285 |
2,060 |
After-Tax NPV6% |
$M |
1,164 |
1,068 |
After-Tax IRR |
% |
25.8 |
29.7 |
Payback |
years |
2.3 |
2.3 |
Key Assumptions (d) |
|||
Palladium Price |
US$/oz |
$1,800 |
$1,725 |
Copper Price |
US$/lb |
$3.70 |
$3.20 |
Platinum Price |
US$/oz |
$1,000 |
$1,000 |
Gold Price |
US$/oz |
$1,800 |
$1,400 |
Silver Price |
US$/oz |
$22.50 |
$20.00 |
Foreign Exchange (“FX”) |
C$:US$ |
1.35 |
1.28 |
Diesel Price |
$/litre |
1.17 |
0.77 |
Electricity |
$/kWhr |
0.07 |
0.08 |
Notes:
|
PROJECT CASH FLOW (After Tax)
PRODUCTION
Palladium (Payable metal)
Copper (Payable Metal)
RESOURCES & RESERVES
The Mineral Resource Estimate below is for the combined Marathon, Geordie and Sally deposits. The Mineral Resource Estimates for Geordie and Sally were prepared by P&E Mining Consultants Inc. (“P&E”). The Mineral Resource Estimate for Marathon was prepared by Gen Mining and reviewed by P&E.
Pit Constrained Combined Mineral Resource Estimatea-j for the Marathon, Geordie and Sally Deposits
(Effective date December 31, 2022)
Mineral Classification |
Tonnes |
Pd |
Cu |
Pt |
Au |
Ag |
|||||
k |
g/t |
koz |
% |
M lbs |
g/t |
koz |
g/t |
koz |
g/t |
koz |
|
Marathon Deposit |
|||||||||||
Measured |
158,682 |
0.60 |
3,077 |
0.20 |
712 |
0.19 |
995 |
0.07 |
359 |
1.75 |
8,939 |
Indicated |
29,905 |
0.43 |
412 |
0.19 |
124 |
0.14 |
136 |
0.06 |
59 |
1.64 |
1,575 |
Meas. + Ind. |
188,587 |
0.58 |
3,489 |
0.20 |
836 |
0.19 |
1131 |
0.07 |
418 |
1.73 |
10,514 |
Inferred |
1,662 |
0.37 |
20 |
0.16 |
6 |
0.14 |
7 |
0.07 |
4 |
1.25 |
67 |
Geordie Deposit |
|||||||||||
Indicated |
17,268 |
0.56 |
312 |
0.35 |
133 |
0.04 |
20 |
0.05 |
25 |
2.4 |
1,351 |
Inferred |
12,899 |
0.51 |
212 |
0.28 |
80 |
0.03 |
12 |
0.03 |
14 |
2.4 |
982 |
Sally Deposit |
|||||||||||
Indicated |
24,801 |
0.35 |
278 |
0.17 |
93 |
0.2 |
160 |
0.07 |
56 |
0.7 |
567 |
Inferred |
14,019 |
0.28 |
124 |
0.19 |
57 |
0.15 |
70 |
0.05 |
24 |
0.6 |
280 |
Total Project |
|||||||||||
Measured |
158,682 |
0.60 |
3,077 |
0.20 |
712 |
0.19 |
995 |
0.07 |
359 |
1.75 |
8,939 |
Indicated |
71,974 |
0.43 |
1,002 |
0.22 |
350 |
0.14 |
316 |
0.06 |
140 |
1.5 |
3,493 |
Meas. + Ind. |
230,656 |
0.55 |
4,079 |
0.21 |
1,062 |
0.18 |
1,311 |
0.07 |
499 |
1.67 |
12,432 |
Inferred |
28,580 |
0.39 |
356 |
0.23 |
143 |
0.1 |
89 |
0.04 |
42 |
1.45 |
1,329 |
Notes:
|
The Mineral Reserve estimate for the Project includes only the Marathon Deposit. The Mineral Reserve Estimate was prepared by G Mining Services Inc.
Marathon Project Open Pit Mineral Reserve Estimatesa-i
(Effective Date of December 31, 2022)
Mineral Reserves |
Tonnes |
Pd |
Cu |
Pt |
Au |
Ag |
|||||
kt |
g/t |
koz |
% |
M lb |
g/t |
koz |
g/t |
koz |
g/t |
koz |
|
Proven |
114,798 |
0.65 |
2,382 |
0.21 |
530 |
0.20 |
744 |
0.07 |
259 |
1.68 |
6,191 |
Probable |
12,863 |
0.47 |
193 |
0.20 |
55 |
0.15 |
61 |
0.06 |
26 |
1.53 |
635 |
P & P |
127,662 |
0.63 |
2,575 |
0.21 |
586 |
0.20 |
806 |
0.07 |
285 |
1.66 |
6,825 |
Note:
- Canadian Institute of Mining, Metallurgy and Petroleum (CIM) Definition Standards for Mineral Resources and Mineral Reserves (CIM (2014) definitions) were used for Mineral Reserve classification.
- Mineral Reserve Estimate completed by Alexandre Dorval, P.Eng., of GMS, an independent QP, as defined by NI 43-101.
- Mineral Reserves were estimated at a cut-off value $16.90 NSR/t of ore.
- Mineral Reserves were estimated using the following long-term metal prices: Pd = US$1,500/oz, Pt = US$1,000/oz, Cu = US$3.50/lb, Au = US$1,600/oz and Ag = US$20/oz, and an exchange rate of 1.30C$ to 1 US$. The pit designs are based on a pit shell selected at a revenue factor of 0.74.
- A minimum mining width of 5 m was used.
- Bulk density of ore is variable and averages 3.1 t/m3.
- The average strip ratio is 2.6:1.
- The average mining dilution factor is 9%.
- Numbers may not add due to rounding.